MODULE 3: PROTOCOLS & ESTIMATES

Submission & Follow-up

Lesson 3.4 - The Billing Blueprint: Mold Edition

1 / 12

When to Submit?

Pre-Approval
Submit before work
Know what's approved
Delays start
Post-Clearance
Submit after done
Faster completion
Risk of reductions
Hybrid (Best)
Preliminary before
Final after clearance
Insurance aware + moving
2 / 12

The Critical Rule

You need clearance documentation
before submitting a final invoice.

No clearance = No proof of completion = No final payment
3 / 12

Complete Submission Package

4 / 12

The Clearance Letter

Include complete clearance report, not just summary letter. If you failed first test, include that too with explanation.
5 / 12

Photo Documentation Organization

Before
Mold extent
Affected areas
Conditions
Containment
Setup complete
Equipment in place
Decon chamber
During
Workers in PPE
Removal process
Bagging
After
Clean surfaces
Ready for clearance
Disposal loaded
6 / 12

Timeline Must Be Logical

Work happens → Clearance test → Pass → Containment down → Job ends

Red flag: Estimate shows work through Jan 15, clearance passed Jan 14
Clearance happens AFTER work complete, not before.
7 / 12

Follow-up Timeline

Day 3
Confirm receipt
Get adjuster name
Day 7
Status update
Any questions?
Day 14
Push for timeline
When decision?
Day 21+
Escalate
Ask for supervisor
Document every communication. Date, time, who, what was said.
8 / 12

Handling Adjuster Questions

Answer professionally with documentation. Reference protocol. Provide calculations.
9 / 12

Key Takeaways

10 / 12

Coming Up Next

Module 4: Advanced Challenges

11 / 12
MODULE 3: PROTOCOLS & ESTIMATES

End of Module 3

Protocols & Estimates Complete

Action Item: Create a submission checklist from what we covered.
12 / 12